Handover is a gate, not a polite email
Follow-on trades should not start because the digger has left. They should start when formation, foundations, drainage interfaces and records meet agreed acceptance criteria. Starting early on soft, wet or incomplete groundworks often creates rework that costs more than waiting for a clean handover.
For inspection culture, see What Building Control Looks For in Foundation and Drainage Works and Building Control inspection stages.
Acceptance criteria that usually matter
| Area | Typically confirm | Why follow-on trades care |
|---|---|---|
| Formation / platforms | Levels, compaction, soft-spot treatment complete | Frame and access depend on stable working platforms |
| Foundations | As-built setting-out; inspection status | Structure starts from verified foundations |
| Drainage | Connections ready or clearly temporary; invert records | Avoid flooded slabs and re-dig under structure |
| Services / ducts | Routes marked; as-builts started | Reduce strike risk for later trades |
| Access & temporary works | Safe access for next plant; edges protected | CDM and productivity for the next package |
| Records | Photos, tickets, inspection notices filed | QA and snagging without archaeology later |
Soft spots and incomplete drainage — common handover failures
Soft spots left ‘to be resolved later’ often become everyone’s problem once scaffolding or frame is up. Incomplete plot or temporary drainage likewise creates standing water that damages formation and delays brickwork.
Agree a soft-spot protocol before peak dig: how they are identified, improved, retested and signed off. Record locations on as-builts.
Records that should travel with the handover
Useful packs typically include inspection notices, concrete tickets where relevant, drainage test results, formation photos, utility as-builts in progress, and a snag list with owners. See groundworks QA and inspection records.
Handover needs a definition before the work starts
A groundworks handover is useful only when everyone knows what is being handed over. One team may think the groundworks are complete when the physical activity is finished. Another may need the area clean, drained, accessible, inspected and documented before the next trade can work safely.
That definition should be written before the package starts. It should name the physical condition, records, inspections and access requirements that make the work acceptable. If the definition is left until the handover meeting, the meeting becomes a negotiation rather than a confirmation.
The handover definition should also say what remains excluded or outstanding. A partial handover can be workable if the limitations are understood. It becomes risky when a follow-on trade assumes an area is complete while drainage, backfill, testing or protection is still unresolved.
The next trade judges handover by usability
Follow-on trades do not judge handover only by whether the groundworks contractor has finished its scope. They judge whether they can start productive work without inheriting avoidable risk. Soft spots, ponding, buried obstructions, missing ducts or incomplete records can all stop the next trade even if the groundworks line item looks complete.
This is why the next trade should influence the handover criteria. Brickwork, frame installation, slab works, services, external works and scaffold all need different conditions. A generic area handed over note is rarely enough for a complex site.
Where several trades follow close behind, the handover should protect sequence as well as quality. A plot or zone may need to be released in a particular order to avoid trade stacking, access conflicts or damage to completed work.
Good handover reduces commercial arguments later
Handover records are commercial protection as well as site administration. They show what condition the area was in when responsibility moved, which tests had been completed, and what exceptions were recorded. That evidence matters if damage, settlement or drainage issues appear later.
A weak handover leaves room for blame to move around the project. The next trade says the ground was not ready; the groundworks contractor says the area was damaged after handover; the client has no clear record of the condition at the transfer point.
The practical fix is simple: make handover a planned gate with named criteria, photographs, records and exceptions. It does not need to become bureaucratic, but it does need to be consistent enough that the site team can rely on it.
Pre-follow-on handover checklist
Before the next trade starts
- Walk the area with groundworks and follow-on supervisors
- Confirm formation and foundation acceptance criteria are met
- Confirm drainage status (permanent, temporary, or not ready)
- Close or formally own remaining soft spots
- File inspection and material records
- Issue a written handover note with outstanding items and owners
For sequencing context, see new-build groundworks sequence or contact the team.
Related services & guides
Continue into the operational pages that sit behind this guidance.
Defining handover criteria on a live package?
Share your drawings and follow-on trade plan — we can discuss practical acceptance checks that usually protect the next stage of the build.
Related insights
More guidance from the Mainline knowledge centre.
Foundations17 min readWhat Building Control Looks For in Foundation and Drainage Works
A practical overview of what Building Control typically reviews on foundations and drainage — hold points, documents and common issues — with caveats that local practice varies.
Last reviewed August 2026Read article
Site Preparation16 min readEnabling Works Before Construction: What Should Be Completed Before the Main Groundworks Package Starts?
What enabling works typically include, where they stop and groundworks begin, and what procurement teams should complete before the main package mobilises.
Last reviewed August 2026Read article
Groundworks15 min readCommon Reasons Groundworks Projects Are Delayed
The programme risks that most often delay commercial groundworks — ground unknowns, utilities, approvals, interfaces, logistics and how to reduce them early.
Last reviewed August 2026Read article